Friday, February 13, 2009
We're movin' right along...
Lots of things happened this week, which was a welcome change from last week when we were waiting on the roof. The stucco finished this week, the roof finished today, the foam insulation started today, a little bit of sheet rock went up in the garage for the insulation to stick to, and we bought our rock today for the outside, fireplace and bar. Check out the progress:
From across the street:
From the right front corner of the lot:
Close-up of the front porch now that the plastic is gone...check out the stain on those columns...
Little better view of the roof:
I don't think I've ever posted a picture of the back corner of the house with the basement storage area under it...here you can also see the chimney!
Another shot of the roof...still in progress:
The garage with sheetrock:
And some of the spray foam on the under side of the roof:
Keep an eye on the blog...they will keep insulating tomorrow and we are insulating some of the interior walls with pink insulation ourselves tomorrow. Also, our rock will be delivered Tuesday and they will start the masonry work then. Spray foam should finish up Monday or Tuesday and then sheetrock will start mid week. Things are happening so fast! It's like, hurry up and wait, hurry up and wait!